Day One |
|
Disassembly Is Started. |
|
The Bus Is Placed On Our Production Line And The
Cradle Is Removed. |
|
|
|
|
Day Two |
|
The Bus Is Placed Over Our 100% Recycling Steam
Pad And Carefully Steam Cleaned To Remove Oil, Grime, Grease And Dirt build
up. |
|
|
|
|
Day Three |
|
The Bus Begins Its Journey Down The Production
Line. |
|
The Needed Structural Modifications To The
Engine Compartment Are Started. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
Day Three Also Marks the Beginning Of Engine
Build Up As well As The Transmission Overhaul. |
|
|
|
|
The Transmissions Are Disassembled And Rebuilt
By Allison Factory Trained Technicians In Our State-Of-The-Art, Allison
Authorized Transmission Shop. |
|
|
|
|
After Carefully Rebuilding The Transmissions To
Allison Factory Specifications. |
|
The Valve Body Is Tested On Our Valve Body
Tester. |
|
Once The Valve Body Test Is Successfully Passed
The Transmission Is Fully Dyno Tested. |
|
|
|
|
Day Four |
|
Engine And Transmission Assembly Continues. |
|
The Rear Bulk Head Is Structurally Modified to
Accommodate The EGR Engine. |
|
Care Must Be Taken To Retain Structural
Integrity After Modifications Are Made. |
|
Structural Modifications To The Bus Are
Completed. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
|
|
Day Five |
|
Engine Buildup Continues. |
|
Transmission Rebuild Continues. |
|
Cradle Assembly Begins. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
Day Six |
|
Cradle Buildup Is Completed. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
Day Seven |
|
Destination Sign Installation Is Started. |
|
Talking Bus Installation Is Started. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
|
|
Day Eight |
|
Cradle Installation Continues. |
|
Destination and Talking Bus Installation Is
completed. |
|
Interior Detail Begins. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
|
|
Day Nine |
|
Complete Cradle Installation. |
|
Properly Secure And Clamp All Lines. |
|
Prepare Bus For Road Test And Ring Out. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
Day Ten |
|
The Installation Is Complete. |
|
Each Bus Is Driven For 100 Miles On The Check
Out Road Test. |
|
Bus Is Inspected For Quality Control
Conformance. |
|
A Quality Control Inspection Is Performed By The
Project Manager And The Quality Control Sheets Are Signed Off |
|
|
|
|
Day Eleven |
|
All Quality Control Lists Are Taken Care Of And
Signed Off. |
|
All Fluids Are Checked And Topped Off. |
|
Wash Bus, And Steam Clean Rims. |
|
Finish Interior Detail And Floor Wax. |
|
A Final Quality Control Inspection Is Performed
By The Project Manager And The Quality Control Sheets Are Signed Off. |
|
|
|
|
Day Twelve |
|
Bus Receives Final Detail. |
|
DDEC Readouts Are Taken As Well Hubodometer
Readings. |
|
A Pre-Delivery Walk Thru And Acceptance Process
Is Conducted With The Customer. |
|
The Bus Is Delivered To The Customer. |
|